Add a delta column in Cost Plan that auto calculates
book
Article ID: 411545
calendar_today
Updated On:
Products
Clarity PPM On PremiseClarity PPM SaaS
Issue/Introduction
Is it possible to add a delta column in the Cost Plan Detail?
This column has to be capable of manual entry of numbers
The number entered should be debited (subtracted) or credited (added) to the Total Cost in the Cost Plan Detail.
Resolution
It is not possible to define a new column that would then affect the 'Totals' column. This cannot be implemented because:
The 'Totals' column derives its values from Time Scaled fields. It indicates the summation of individual values over a period of time, of those Time Scaled columns / fields. Defining a column of 'number' data type will therefore not come under the purview of the 'Totals' column
In addition to this, the 'Totals' column considers one Time Scaled column at a time. It does not show values based on Time Scaled values in two or more columns.