DWH_INV_SUMMARY_FACTS table: No data for Material and Expense resources
book
Article ID: 410949
calendar_today
Updated On:
Products
Clarity PPM On PremiseClarity PPM SaaSClarity FedRAMP
Issue/Introduction
Material and Expense resource cost data is not populated on the DWH_INV_SUMMARY_FACTS table
STEPS TO REPRODUCE:
Create a project
Add a Labor resource and a Expense, Material and Equipment type non-labor resources as Staff members
Create a task and assign all 4 members to the task and add some ETC
Add the rate matrix information to the project for the 4 type resources
Run the Rate Matrix Extraction job and Update Earned Value and Cost Totals job
At assignment, task and project level we can see the ETC Cost populated
Run the Load DWH job
Look at the DWH_INV_SUMMARY_FACTS table in the Data Warehouse. Look at columns like: etc_expense_cost, etc_material_cost, etc_equip_cost, etc_labor_cost
Expected Results: Data is populated for all type of resources Actual Results: Data is only populated for Labor and Equipment resources. Data for Material and Expense resources is not populated
Same happens to EAC Cost, Allocation Cost ... Only labor and Equipment data semes to be populated at the DWH_INV_SUMMARY_FACTS table
Environment
Clarity 16.2.3.5, Clarity 16.3.3, 16.4.0
Cause
DE176048
Resolution
Fixed in:
Clarity 16.4.1
Clarity 16.4.0 Patch 1 (16.4.0.1)
Clarity 16.3.3 Patch 2 (16.3.3.2)
Additional Information
In Broadcom SaaS Prod this will be fixed together with Production upgrade to 16.4.0 as per SaaS Upgrade Schedule