Issue/Introduction

Hierarchy Task module Timeline view does not load if the View Options Color By is set to fields like Start, Finish, ACWP, % Complete

STEPS TO REPRODUCE:

  1. Go to MUX > Administration > Blueprints
  2. Create a copy of the Standard Investment Hierarchy blueprint
  3. Add the Tasks module to the same
  4. Go to MUX Hierarchies and create one. Link it to the above blueprint
  5. Add a few investments to the hierarchy
  6. Go to the Tasks module. The tasks of the associated investments are seen
  7. On the Calendar view > View Options > Color > Status can be selected and the Calendared view will be colored accordingly
  8. On the Board view > View Options > Color > Status can be selected and the Board view will be colored accordingly
  9. Go to the Timeline view > View Options > Color By > Status can be selected and the Timeline view Gantt will be colored accordingly
  10. Notice that on the Color By option you can select any Tas object field like Start, Finish, ACWP, % Complete ....
  11. Select any of those

Actual Results: The Timeline view loads blank when a field not 'allowed' is selected. No data displays.
Expected Results: The Color By drop downs should be restricted to the 'allowed' fields as is done in the Calendar and Board views.

Environment

Clarity 16.2.3, 16.3.X

Cause

This is caused by DE176018

Resolution

This is fixed in:

  • Clarity 16.4.0
  • Clarity 16.3.3.2