Unable to assign license to vCenter 9.x after evaluation license expiry, Assign Primary License option is greyed out for vCenter
book
Article ID: 410303
calendar_today
Updated On:
Products
VCF OperationsVMware vCenter Server
Issue/Introduction
VCF licenses are generated from Business Service Console, and it's added to VCF Operations instance. However, unable to assign the license to the vCenter.
vCenter selection is greyed out while following the Assign Primary License procedure to assign the license to the vCenter.
The Assignable column shows No with the message "To assign this license, it must have allocated capacity of ### cores." as shown below:
Environment
VCF 9.x
Cause
This issue is observed when the license does not have enough capacity to assign to the vCenter (Available CPU cores in license < Actual CPU cores usage on vCenter).
Resolution
Perform any of below steps depending on the CPU cores availability in default license:
Unassigned CPU cores are available in default license.