The Actuals on Task in Project is not matching the the Actuals in the Assignments
v16.3.2
Due to WBS sequence issue on the tasks.
Actuals on Task tab is calculated by function PRJ_EFFORT_FCT. It calculates the sum of actuals on the task based on the following logic:
(t.prwbssequence >= wbsInfo.prwbssequence and t.prwbssequence < wbsInfo.WBS_NNBSEQ)
The actuals mismatch on Task and Assignment is due to the Wbssequence on the tasks. Fix the WBS sequence issue on the tasks.