When a labor resource 'A' is staffed on a Team Investment and the Team investment is allocated to a Project and assign to a task on the same project then in Modern UX Timesheet after logging into Clarity as Resource 'A', clicking on 'Add Tasks' button -> 'Select Tasks', Filtering on
'Assigned Resources' is set to resource 'A', no task gets displayed.
Expectation is that the Task that the Team investment is assign which resource 'A' is part of should display.
If the user clicks on 'Add Tasks' button -> 'Add Assigned Tasks' then the Task on the Project does display.
Steps To Reproduce:
1. Add a labor resource 'A' to a Team investment
2. Allocate Team investment to a Project and assign to a Task
3. Grant the following access rights to labor resource 'A'
- Timesheets - Edit All
- Timesheets - Navigate
4. Log into Clarity as labor resource 'A', Navigate to Timesheet page in MUX
5. Click on 'Add Tasks' button -> 'Select Tasks'
6. Filter on the Timesheet page by setting 'Assigned Resources' = Resource labor 'A'
Expected: The Task that Team Investment is assigned which labor resource 'A' is part will display
Actual: No Task gets displayed. Clarity is not recognizing resource 'A' is assigned to a Team
Clarity 16.3.2, 16.3.3
DE174530
This has been determined not to be a bug.
This Timesheet area was not designed as a requirement in this field for filtering.
This is a Multi-Select filter and want a user to specifically determine if they want to filter for Tasks directly assigned to their name or they can pick the Team(s) that they are a member to do the filtering.