Project locks are appearing randomly
search cancel

Project locks are appearing randomly

book

Article ID: 406998

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Some projects are getting an Import/Export lock.  The resource that shows 'Locked By' has never worked on the project.

Cause

There were two Update Investment Allocations and Usage jobs running at the same time

Resolution

Cancel/reschedule one of the Update Investment Allocations and Usage jobs so they do not conflict.  Or under Administration>>Reports and Jobs, set the job incompatible to itself.