The user is unable to edit any properties on a Custom Investment when the Investment Dates are the same, without any staff or tasks and a Cost Plan has been created.
Steps To Reproduce:
Expected Results: The attributes should be to be changed.
Actual Results: The toast message appears INV-0024: Forecast Cost Finish date is earlier than Forecast Cost Start date
Clarity 16.3.2, 16.3.3
DE174171
Fixed in
Workarounds: Add Staff or Add a Task with a duration longer than a day
Note: The resolution mentioned in INV-0024: Forecast Cost Finish date is earlier than Forecast Cost Start date does not apply to this use case