Working with Frictionless timesheets, and noticing that for some users, the total hours are less than expected. Upon review, some of the time entries did not get created on the timesheet in Clarity after running Timesheet Integration job
Environment
All Supported Clarity Releases
Resolution
Checklist in case of missing time entries:
Team Investment has to be Active in Clarity and have Start/Finish date that cover the period you're looking for
The Resource has to be added on that team, with a non-0 allocation
The Resource has to have time allocated on that Team for that week (check in Per Period metrics). 0 allocation or negative allocation will not be brought in
In Rally, the Feature has to have a parent Epic for it to have been brought up to Clarity
In Rally, make sure the User Stories are in progress and have Plan Estimate
Jobs have to be run in correct order, Rally Sync jobs first, then Timesheet Integration jobs.
Note: After running the Timesheet Integration job, check the Job Logs and take notes of any features that are not included. Also check for any warnings and errors.