When using autoschedule on a project, the task date is changed to 6/2/2079. This happens in MUX and Classic
Steps to Reproduce:
Expected Results: The task will be autoscheduled correctly, dependent on the start date
Actual Results: The task start and finish date changed to 6/2/79
Clarity 16.3.0, 16.3.1, 16.3.3
This was analyzed through DE173848
When a Staff Member does not have any capacity due to zero allocations, the auto-scheduler cannot determine the next available date to schedule a task with an ETC amount. It will keep trying to find a future date where the resource has allocations for the project, and it will keep going until it hits the internal system limit date of June 2, 2079.
If you would like to use auto-schedule, you will need to provide non-zero allocations or 'Lock' the Task.
If the Task is 'locked', it will NOT move when using auto-schedule.
Workaround
Either of the below will avoid the tasks being pushed to 2079