To Dos are not showing up in the To Do Module if tasks are being copied from another custom investment/project in the Tasks Timeline view.
Steps to Reproduce:
Expected Results: All To Dos, including the one which got copied using 'Copy from...' option in the Tasks Timeline view should show up in the To Do Module.
Actual Results: Only To Dos which got copied through Template are being shown up.
Workaround: Use Task Module to view the list of To Dos.
16.3.0, 16.3.1, 16.3.2, 16.3.3
DE173301
Fixed in:
Note 1: As part of this defect fix, the below issue is also resolved
Summary: The Task Details 'To Dos' sub-tab is not getting refreshed with the correct list of To Dos when switching between Task rows.
Expected Results: The Details To Dos sub-tab should display the correct list for each Task.
Actual Results: I see the same To Do items when clicking on different Task rows.
Note 2: Error: API-1005 appearing when changing the view out of the Task Details Fly Out and vavigating between Grid, Timeline, and Board views causes a failure in the To-Do fly-out to load data, accompanied by API-1005 error.
This issue only happens in 16.3.3 Patch #2. It does not occur in Release 16.4.0.
Cause: Due to DE182296
Resolution: Fix is backported to v16.3.3 patch 4