Issue/Introduction

The Tasks workspace looses the Assigned Resources filter field value when the Assignments module is expanded and closed on a selected task and afterward a new project is expanded on the timeline

STEPS TO REPRODUCE:

  1. Create a project Project1
  2. Assign Res1
  3. Create 2 tasks and assign the Resource to only 1 of them
  4. Create a new project project2
  5. Assign Res1 to the project
  6. Create 2 tasks and assign him only to 1 of them
  7. Go to MUX > Tasks workspace > Timeline view
  8. Add the Assigned Resources field to the filter and add Res1 to it
  9. The 2 projects get filtered out and if we expand those we only see one tasks
  10. Expand the 1st project, select the task and open the Details pane
  11. Go to Assignments > Click Expand and close the assignments menu
  12. Back on the Timeline view, expand the 2nd project

Expected Results: Only the task where the resource is assigned is visible
Actual Results: Both tasks are visible, also the one where the resource is not assigned 

Environment

Clarity 16.3.2

Cause

This is caused by DE173252

Resolution

This is fixed in Clarity 16.4.0

Workaround: Refresh the page