Project % Complete field does not have a validation range and you can enter a value which is higher than 100%.
Steps to Reproduce:
Create a project (or Custom Investment type)
Create a task
At the task grid, add the % Complete field
Set the value to 150% or a negative value such as -40%
The value is not saved and you get an error: PRJ-07231: Invalid number. Enter percent complete in the range of 0 to 100
Add the '% Complete' and '% Complete Method' field to the project grid
Find a Project that uses the 'Manual' method and set the value to 150% or a negative value such as -40%.
Expected Results: The value should not get saved and a Toast message should appear: 'PRJ-07231: Invalid number. Enter percent complete in the range of 0 to 100.'
Actual Results: You do not get a validation error and can save a 150% value or a negative (40%) value.