We have a business rule in a project blueprint where the task start and finish dates are disabled for edition when the task status is set to Completed.
However, when accessing to the tasks timeline, the task can be dragged and dropped and date changes occur ignoring the blueprint rule.
STEPS TO REPRODUCE:
Expected Results: The task can not be dragged and dropped as otherwise the dates are changed
Actual Results: The task can be dragged and dropped and dates are changed
Clarity 16.2.1, 16.2.2, 16.2.3, 16.3.0, 16.3.1
This is caused by DE165314
This is fixed in Clarity 16.3.2