External Dependency Task is set to 'Start-Start' if the default isn't changed
book
Article ID: 402838
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity FedRAMPClarity PPM On Premise
Issue/Introduction
When an External Dependency is created, the default value is specified as 'Finish-Start', if the type is not adjusted, the type will be set as 'Start-Start', when the Dependency is created.
STEPS TO REPRODUCE -
1. In the Modern UX, open any project and navigate to the Tasks module in the Timeline view.
2. Select a task and open the menu by right-clicking on it.
3. Select 'Add External Dependency'.
4. Select an Investment and a Task. Leave the Type as the default 'Finish-Start'
5. Click Add
EXPECTED RESULTS:
The Dependency will be created with a Type of 'Finish-Start'
ACTUAL RESULTS:
The Type is 'Start-Start'
Environment
Clarity 16.3.2
Resolution
The resolution is included in 16.3.3. This was originally tracked as DE172517.
Workaround: During the Dependency creation, first select a different Type, and then change it back to 'Finish-Start' before clicking 'Add'