Issue/Introduction

In 16.3.2 Roadmap Items timeline view, the details flyout for Linked To attribute does not open the linked to investment when it is clicked. Nothing happens.

STEPS TO REPRODUCE:

  1. Open a roadmap with linked investments
  2. Go to the timeline page
  3. Click on one of the linked investments on the timeline to open the details flyout.
  4. If the Linked To attribute is not configured in the flyout add it.
  5. Click Done
  6. Click on the Linked To item in the flyout

Expected Results:  The investment opens within the roadmap workspace.

Actual Results:  The link does not respond

Environment

Clarity 16.3.2

Cause

This is caused by DE171458

Resolution

This is fixed in Clarity 16.3.3

Workaround:  Use grid, or change the linked to to another investment and then change it back.  Once there is an update to the field, the link then works.