In 16.3.2 Roadmap Items timeline view, the details flyout for Linked To attribute does not open the linked to investment when it is clicked. Nothing happens.
STEPS TO REPRODUCE:
Expected Results: The investment opens within the roadmap workspace.
Actual Results: The link does not respond
Clarity 16.3.2
This is caused by DE171458
This is fixed in Clarity 16.3.3
Workaround: Use grid, or change the linked to to another investment and then change it back. Once there is an update to the field, the link then works.