Threshold coloring is not displayed in Resource Availability when availability is zero
search cancel

Threshold coloring is not displayed in Resource Availability when availability is zero

book

Article ID: 399436

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise Clarity FedRAMP

Issue/Introduction

In the Staffing – Resource Availability portlet, when a resource's availability for a given time period is zero (0) but assignments exist within that same period, the cell value is not colored according to the configured threshold settings.

 

Steps To Reproduce:

  1. Create a project with a one-year duration (e.g., 1 Jan 2025 – 31 Dec 2025).
  2. Allocate a labor resource to the project.
  3. Set the resource calendar to non-workday for the entire month of July 2025.
  4. Create a task with the same duration as the project and assign the labor resource to the task.
  5. On the Task – Assignments page, enter 40 hours of ETC (Estimate to Complete) for the resource.
  6. In the Modern UX, navigate to User Profile Settings > General tab, and locate the Thresholds section.
  7. Configure the following threshold parameters:
    • Set Over Allocation to 5%
    • Set Over Assignment to 5%
    • Set Over Color to Red
  8. Navigate to the Staffing – Assignments by Resource page.
  9. In the View Options panel, select ETC under the Assignments Display section.
  10. In the Resource Availability portlet, filter for the resource assigned in Step 4 and review the data for July 2025.

Expected Results: The cell for July 2025 should be highlighted in Red, as the resource's assignment exceeds their available hours.

Actual Results: The cell for July 2025 is not highlighted and does not apply the configured threshold coloring.

Environment

Clarity 16.3.1, 16.3.2

Cause

DE171155

Resolution

This behavior is currently working as designed.

To determine threshold coloring, the application calculates percent utilization using the following formula: Percent Utilization = Allocation/Availability