Tasks in a Timesheet get misaligned
search cancel

Tasks in a Timesheet get misaligned

book

Article ID: 397350

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Steps to Reproduce:
    1. Login to the Modern UX
    2. Create two Projects
    3. Assign a team member to both these Projects
        (Projects -> Staff tab)
    4. Create a Task with the following name in the first project
        Task Name: "placeholder"
    5. Create a Task with the following name in the second project
        Task Name: "placeholder placeholder placeholder placeholder placeholder placeholder placeholder placeholder placeholder placeholder placeholder placeholder "
    6. Assign the same resource as in step 3 to both these Tasks
    7. Navigate to 'Timesheets' module. Open the Timesheet of the resource from step 3
    8. Do not have the web browser occupy the entire screen at this point. Add the Tasks created in steps 4 and 5 to this Timesheet
    9. Now, enlarge the browser window by dragging it

Expected Results: Both the Tasks added to this Timesheet remain aligned.

Actual Results: The Task created at step 5 becomes misaligned at some point while enlarging the browser. This typically happens only with large displays.

Environment

Clarity 16.3.1

Cause

DE170443

Resolution

DE170443 is fixed in Clarity 16.3.3.