STEPS TO REPRODUCE:
- Set Locale to Japanese in Settings - General
- On the project task timeline, the monthly period display shows "yy年m月月" instead of the correct "yy年m月"
- The character "月" (month) is duplicated
Expected Result: Single month value should be shown.
Actual result: Month value is duplicated.
Resolution
DE170327, fixed in 16.3.3