Looking for rescheduling settings at the job and extended calendar levels.
Rescheduling rules like "Holiday Action" and "Non Workday Action" and "Date Adjustment" and extended calendar keywords like MNTHD#02 are only available in the calendar definitions themselves, not in the job definitions.
Job definitions offer scheduling settings, not rescheduling settings.
The job definition scheduling settings available are:days_of_weekexclude_calendarmust_complete_timesmust_start_timesrun_calendarrun_windowstart_minsstart_timestimezone