User tries to add a resource to a project under Project>>Staff using the plus sign ( + ). The user receives the below error
API-1019: could not process the request due to internal error.
Using the Add Staff button works correctly.
The Per-Period Metric dates in View Options were not near the duration of the project.
Ex-
Project Start - 1/1/2025
Project Finish - 1/31/2025
View Options Start - 1/1/2026
View Options Finish - 1/31/2026
Update the View Options start and finish dates to include the project duration