Unable to indent a task in PPM if it's a Milestone
search cancel

Unable to indent a task in PPM if it's a Milestone

book

Article ID: 3931

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Unable to indent a task in PPM if it's a Milestone, receive error:

PRJ-07203: Invalid indent. A milestone cannot be turned into a summary task.

Steps to Reproduce:

    1. Create a new project in PPM

    2. Create two tasks in the project:

  • Task1: Milestone task 
  • Task2: Not a milestone

    3. Attempt to make Task1 a summary task:

  • Go to the Gantt
  • Click the check box next to Task2
  • Click the Indent button

    4. Open the project in MSP

Expected Results: No error message is shown and the task is able to be indented to make it a summary task

Actual Results: Unable to indent the task, and receive error "PRJ-07203: Invalid indent. A milestone cannot be turned into a summary task."

Environment

Applies to all supported PAS environments.

Cause

This is due to current design of PPM

Resolution

This is working as designed. PPM does not allow summary tasks to be milestones. To request an enhancement to change this behavior, we encourage you to submit an idea from our Communities site.

Additional Information


Reference kb000007164: Summary tasks that are Milestones do not Export as Milestones in MSP
Reference kb000035333 What are the rules to 'outdent' and 'indent' tasks on a project?