Unable to indent a task in PPM if it's a Milestone, receive error:
PRJ-07203: Invalid indent. A milestone cannot be turned into a summary task.
Steps to Reproduce:
1. Create a new project in PPM
2. Create two tasks in the project:
3. Attempt to make Task1 a summary task:
4. Open the project in MSP
Expected Results: No error message is shown and the task is able to be indented to make it a summary task
Actual Results: Unable to indent the task, and receive error "PRJ-07203: Invalid indent. A milestone cannot be turned into a summary task."
This is due to current design of PPM
This is working as designed. PPM does not allow summary tasks to be milestones. To request an enhancement to change this behavior, we encourage you to submit an idea from our Communities site.
Reference kb000007164: Summary tasks that are Milestones do not Export as Milestones in MSP
Reference kb000035333 What are the rules to 'outdent' and 'indent' tasks on a project?