Edays in MSP are changing when saved to Clarity.
search cancel

Edays in MSP are changing when saved to Clarity.

book

Article ID: 392057

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

A user creates a project in MSP with the duration set to 30 edays.  When a resource is assigned and then saved back to Clarity the dates change.  Clarity is still recognizing the resource's non-working days.

Environment

Clarity v16.3+

Resolution

When using edays, the project should be created in Clarity first and then opened in MSP to make changes.  If the project is created in Clarity first, the non-working days will be removed from the resource's calendar and the dates will persist.