Common grid view Per period Metrics show wrong figures at the grouped by row when the View Options are set to Grand Totals and Effort displays in days
Steps to Reproduce:
- Classic Administration > Project Management > Base Calendars
- Create a 37.5 hour calendar and set it as Standard.
- Set the calendar shifts to 7.5 hours daily
- Create a resource and add the above calendar to the same
- Create a project that spans from 03/01/25 to 03/31/25
- On the Staff tab add the allocation field to the Per Period Metrics
- Group by Resource
- User settings > Set Effort to Hours
- View Options:
-
- Periods > Project Start - Project Finish
- Totals > Sum of Periods
- Totals displays 157.50 (21 days x 7.5 hours) hours for the resource row as well as the group by row
- View Options:
-
- Periods > Project Start - Project Finish
- Totals > Grand Totals
- Totals displays 157.50 (21 days x 7.5 hours) hours for the resource row as well as the group by row
- Change User settings > Set Effort to Days
- View Options:
-
- Periods > Project Start - Project Finish
- Totals > Sum of Periods
- Totals displays 21 days for the resource row as well as the group by row
- View Options:
-
- Periods > Project Start - Project Finish
- Totals > Grand Totals
Expected Results: Totals displays 21 days for the resource row as well as the group by row
Actual Results: Totals displays 21 days for the resource row but 22.50 for group by row.
The group by row is calculated by 7 hours (157.5 hours / 7 hours) a day instead of 7.5