Cost Plan Totals Not Calculated: View Options Duration >100 periods
search cancel

Cost Plan Totals Not Calculated: View Options Duration >100 periods

book

Article ID: 390097

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

For cost plans, the actuals totals are not calculating when the weekly number of periods are set to 100 or more.

Valid range 1 - 99

Environment

16.3.1

Resolution

This is by design and not able to be configured in the UI.