The synchronization fails to update Rally > Feature > State to JIRA > Epic > Status
Steps to Reproduce:
1: Create a bidirectional Automation between Rally and JIRA of type synchronization and conflict management strategy as First In
2: Map Fields as below
3: Set below value mappings
4: Under field configuration set "Synch Value Type" as By Value
5: Create a EPIC in JIRA and run the automation, it will create an EPIC and Rally and will set the State correctly
3: Try to change the State in Rally to Backlog and the automation will fail to synch to Status in JIRA.
Expected Results: The synchronization should be able to set the value as per the value mapping.
Actual Results: The synchronization fails with below error.
ERROR java.lang.Exception: Exception occurred while updating status of the record. Attempted transition to Backlog() but the current transition is 10034(Backlog)
ConnectALL: 3.6.0, 3.8.0
DE167329
DE167329 Fixed in 3.8.0