The resource allocation for a project staff member is reset to zero after the termination date, but the remaining allocation continues to be reflected.
Steps to Reproduce:
Expected Results: Both Allocation and Remaining Allocation should be cleared after the termination date.
Actual Results: Allocation is cleared, but Remaining Allocation remains. Running the Time Slicing sync job with the "Force Update" option removes the Remaining Allocation.
Clarity 16.3.1 and lower
This is caused by DE167320
This is fixed in Clarity 16.3.2
For release prior to Clarity 16.3.2, execute the Time Slicing job with force update flag during non business hours