Symptoms:
The Pending Estimates value is not matching the ETC value from the assignment.
Steps to Reproduce:
- Create a project in PPM (03-NOV-2015 thru 24-NOV-2015)
- Make sure that project and task dates fall under the current dates
- Add two resources to the team
- Create a task with same duration as of project and assign both resources to the task
- Add some proposed ETC (16 hours) to one assignment
- Post some actuals(40 hours) for the week(11/9/2015) on the other resource
- Add some ETC(16 hours) for the second assignment
- Make the starting day of the week(11/9/2015) the week that resource posted actuals in step #5 as "Non-Workday" in the calendar
- Open the project in OWB
- Go to Controlling "Status Update" view to check the Pending ETC [CA Time](Hours) column for the assignment whose actuals are posted
- In the Project Tab , click on Pending Estimates and accept pending estimates, the ETC will be overwritten to zero
Expected Result: Pending ETC should be the ETC for the assignment
Actual Result: Pending ETC is Zero
Cause:
Caused by CLRT-79219
Resolution:
Resolved in CA PPM 14.3 Generic Patch #5
Additional Information:
Reference TEC1696455 : PPM 14.3 Generic Patch available to resolve reported issues