MUX - When adding/removing via Assigned Resources on tasks getting an error when one of the resources already on it is inactive.
search cancel

MUX - When adding/removing via Assigned Resources on tasks getting an error when one of the resources already on it is inactive.

book

Article ID: 387765

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When adding/removing via Assigned Resources attribute on tasks using details flyout getting an error when one of the resources already on it is inactive.

Steps to Reproduce: 

1. Login to MUX
2. Open one of the existing projects.
3. Go to Staff and add some resources.
4. Navigate to Tasks->Details Flyout and assign some resources to the Task using Assigned Resources attribute.
5. Inactivate one of those resources that were assigned in Step 4 above.
6. Go back to Tasks->Details Flyout and attempt to add another resource or remove one of the existing resources, notice error below:
CMN-0009: Attribute 'Assigned Resources' has invalid Lookup Value '[T1234567, T7654321, T9874561]'

Expected Results: it should allow to add/remove resources

Actual Results: it throws an error.

Environment

Clarity 16.3.0, 16.3.1

Cause

DE165988

Resolution

Fixed in 16.3.2 and 16.3.1.1 (16.3.1 Patch 1)

The 'staffed' members that are inactive will appear while browsing, however, inactive resources not already staffed will not appear while browsing.