All "To Dos" information from an Idea isn't getting moved to the Project when the Idea is converted.
1. Ensure that you are using an Idea and Project Blueprint that adds the "To Dos" module.
2. Create a New Idea, associate it to the created Blueprint. Create Risks, Issues, or Changes. To the items that were created, click the "Details" tab, and add "To Dos"
3. Access the "To Dos" module (that was added to the Blueprint). You will see the To Dos that were created.
4. Convert the Idea to a Project.
5. View the Risks/Issues/Changes and they will be copied, and their associated "To Dos". The To Dos module, however, is empty.
Expected Results:
The To Dos that are associated to the Risks/Issues/Changes would display on the Project, as it displayed in the Idea
Actual Results:
They do not display
Workaround:
None
NOTE: In 16.3.0, the To Dos tab of the "Idea" doesn't display the To Dos either.
Clarity 16.2.1
DE165152
Resolved in 16.3.2.