Issue/Introduction

Storage vMotion between the vSAN8 datastores is failing using the workload optimization feature under Aria Operations 8.18.x.

Failed waiting for data. Error 195887107. Not found. 2024-11-21T12:01:45.406626Z The migration transfer failed during the receive operation to socket 73820494832112: received 0/36 bytes: Connection reset by peer. vMotion migration [177657948:8194800544560023648] failed to read stream keepalive: Connection reset by peer Migration to host <IP_ADDRESS> failed with error Connection reset by peer (195887179). 2024-11-21T12:01:45.592395Z vMotion migration [177657948:8194800544560023648] failed to get DVS state in the restore phase from the source host <IP_ADDRESS>

Environment

Aria Operations 8.18.x

Resolution

The fix will be released in the next upcoming HF release.