The Jobstream execution shows incorrect workflow executions when workflows are scheduled using JSCH object
search cancel

The Jobstream execution shows incorrect workflow executions when workflows are scheduled using JSCH object

book

Article ID: 382157

calendar_today

Updated On:

Products

Automation Analytics & Intelligence

Issue/Introduction

The workflows JOBP.EXP.FRA, JOBP.EXP.UKI, JOBP.EXP.FIN and JOBP.EXP.EMEA are scheduled using JSCH object. All these workflows are scheduled to execute at 9Am, 11AM, 1PM, 3PM and 5PM. All these workflows contans tasks(ex. JOBS, SCRI, etc...)

When creating a Jobstream for a JOBS(as  a target job), which is a task within the workflow JOBP.EXP.EMEA , the execution of the Jobstream shows all the workflows as shown below.

Jobstream execution showing all workflows:

 

Environment

Products: Automation Analytics & Intelligence, Automic Workload Automation v21.x, 24.x

Cause

By design

Resolution

There are two options for narrowing in the gantt display.

Option #1:   All other objects that the user does not want to see can be added as Trim Points.

 

Option #2: The desired/expected workflow(s) can be added as Start Jobs.