Hiding External Dependencies in Tasks Timeline View
search cancel

Hiding External Dependencies in Tasks Timeline View

book

Article ID: 382090

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Clarity 16.2.1 implements an enhancement in the Tasks Timeline view, as it allows you to Add and Display External Dependency Tasks.

Is there any way to hide External Dependencies in the Timeline View?

Environment

Clarity 16.3.0.

Resolution

This is currently not possible, and should be logged as an enhancement with Product Management.

Additional Information