Clarity 16.2.1 implements an enhancement in the Tasks Timeline view, as it allows you to Add and Display External Dependency Tasks.
Is there any way to hide External Dependencies in the Timeline View?
Clarity 16.3.0.
This is currently not possible, and should be logged as an enhancement with Product Management.