In Modern UX, when you want to add a task to the timesheet, the Select Task view appears. The ETC displayed for the available tasks does not match the ETC of the tasks once added to the timesheet.
The Select Tasks window, shows data at task level and the timesheet added tasks show data at assignment level
The ETC displayed on the Select Tasks window is the ETC on the assignment PLUS any pending Actuals (pending actuals is hours on any timesheet that have not posted)
The timesheet displays the ETC of the assignment MINUS any pending actuals. The ETC will decrement once you add hours to the timesheet.
- This number does not change when viewing timesheets for previous weeks since it uses current assignment ETC PLUS pending actuals.
Once timesheets post and there are no pending actuals, the ETC will match for all areas.
Note: If loading pattern = Fixed, when you add hours to the timesheet the ETC will not decrement on the timesheet until the hours are posted.