How can I make Investment Start and Finish Dates required in both Classic and MUX?
search cancel

How can I make Investment Start and Finish Dates required in both Classic and MUX?

book

Article ID: 381354

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

You are looking for the ability on the Investment or Idea object to make this start and finish fields as required. Do we have an options to accomplish this in both Studio and Blueprint for MUX?

Environment

16.x

Resolution

For Classic for these 2 required you would need to follow below steps:

1. Administration->Studio->Idea object and then ckick on Views tab.

2. Then go to Fields (screenshot below) and you can find both start and finish dates and make them required.

For MUX:

1. Go to Administration->Blueprints

2. Add Business Rule to the Idea blueprint as below