hyperv probe is not taking the port, PID & Address and gives the error message below:

Controller: Max. restarts reached for probe 'hyperv' (command = hyperv.exe)



 

Environment

UIM Any Version

Robot Any version

Cause

PPM (Probe Provisioning Manager) is not deployed on robot.

Resolution

Follow the below step:-

1.  Redeploy the java_jre 1.71

2.  Install the .net 3.5 on the server and restart the services.

3.  Deploy the PPM 3.24 probe

4.  Upgrade the hyperv probe from 2.20 to 3.10

Additional Information