Idea Create from Template adding month to cost plan
search cancel

Idea Create from Template adding month to cost plan

book

Article ID: 381139

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

If the idea template start date is not the 1st of the month when creating a new idea from the template is adding an additional month to the cost plan.
 
 
STR:
 
1.  Create an Idea to use as template
a.  Start and Finish dates = June 26, 2024
b.  Create a manual cost plan with plan dates Jan thru Dec 2024 (create one detailed row)
 
2. Create a new idea from the template
a.  Start and Finish dates = Nov 26, 2024
 
 
Expected Results:   New Idea plan dates are 12 periods, these may be set off from the original idea start date to the new idea start date as documented.  
 
Actual Results:     The plan start date is offset as expected, but an extra month is added to the end of the plan.
 
Workaround:  If this does happen, manually update the new idea's cost plan to remove the additional month.

 

 

 

 

 

Environment

16.2.3

Resolution

Reported as DE155874.  Fix targeted for 16.3.1