Problem:
Work hour is truncated if a task (and project) begins on a non-work day.
Steps to Reproduce:
1. Create a project in PPM
2. Add a team member to the project
3. Create a task with a start date on a Saturday and assign the team member to the task with some remaining work
4. Export the plan to MSP
5. Review the task
Expected Result: Task starts on Saturday with remaining work
Actual Result: Task turns into a milestone with 0 remaining work
Cause:
Caused by CLRT-79645
Workaround:
Set the task Start Date to a work day.
Resolution:
Based on the complexity of the fix, this issue will not be fixed at this time. Please create a Support case if the workaround is not feasible for your use case.