A user is unable to use xog on a cost plan where one of the grouping attributes is blank.

Steps to Reproduce

  1. Create a project with resources and roles on the team
  2. Create a new Cost Plan using Resource as the grouping attribute
  3. Populate the Cost Plan
  4. Try to xog out the costplan

Expected Results - You can xog out successfully

Actual Results - You receive an error and are not able to xog out the cost plan

 

Resolution

This is by design.  If a cost plan is xogged and one of the grouping attributes is null on the xog file, the plan cannot be copied or submitted for budget.