Issue/Introduction
Steps to Reproduce:
- Create an automations between ADO(Feature) -> MSPS(Task)
- Map field Assigned To(ADO) -> Assignment(MSPS) along with other fields. See screen capture for reference.
- Create Feature on ADO and set Assigned To
- Run the automation and see if the Feature is synced to MSPS.
- Now Rerun the automation and verify it is updated on MSPS side.
Expected Results:
If the Assigned To value is present, it should be updated on MSPS.
Actual Results:
Assigned To field does not always sync to MSPS.
Resolution
DE152994 is resolved in ConnectALL 3.6.0 and ported back to 3.5.0.2