Steps to Reproduce:
1. Create a project in PPM and add one team member to the project
2. Create a fixed duration task with a duration of more then one day. For this example: Start = 10/15/14 , and Finish = 10/29/14
3. Assign the team member to the task with Loading pattern = Uniform
4. Export the project to MSP and review the task duration
Expected Result: The duration of the task is 10 days with Start/Finish Dates of 10/15/14 - 10/29/14.
Actual Result: The duration of the task is changed to 1 day with Start/Fijnish dates of 10/15/14 - 10/15/14.
Applies to 14.2 base through 14.2 patch 5 new driver.
Caused by CLRT-76387
This has been fixed in PPM 14.2 patch 6 and 14.3
No identified workaround aside from changing the task type to something other then Fixed Duration.