Issue/Introduction

At Modern UX -> Projects -> Staff tab, it is noticed that Fiscal Periods (defined in Administration -> Entities) are used to show time scaled values, instead of calendar periods. Is this behaviour configurable? That is, can the time scaling be done using calendar periods, instead of fiscal periods?

Environment

Version: 16.2.3.

Resolution

As of the version mentioned above this is non-configurable.