Remaining Capacity on Roadmap Items is showing values in a wrong unit
search cancel

Remaining Capacity on Roadmap Items is showing values in a wrong unit

book

Article ID: 376618

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

The Remining Capacity is calculated correctly as per formula (Capacity - Actual) in Roadmap Items. But it is not showing the values in the correct Unit of Measureas whereas the other fields like Capacity and Actual display values as per the selected Unit of Measure. It is showing the values of it in seconds irrespective of the measure that is set (Hours/Days/FTE)

Steps to Reproduce:

  1. Login to New UI
  2. Navigate to Roadmaps -> Roadmap Items
  3. Import couple of projects onto the Roadmap
  4. Configure the Roadmap item grid view to display TSV fileds Remaining Capacity and Capacity
  5. Configuren the setting in New UI to display the Unit of Measure as Days
  6. Observer the values of Remaining capacity and Capacity on the Roadmap items
  7. Now change the Unit of Measure as Hours

Expected Results:
The value of Remaining capacity and Capacity should change as per selected Unit of Measure

Actual Results:
The value for Remaining Capacity remains the same and the capacity changes as per selected Unit of Measure

Environment

16.2.2

Cause

Due to DE153584

Resolution

DE153584 is fixed in v16.3.0.