WBS Sort number duplicates when adding a new task
book
Article ID: 375100
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
When adding a new task the WBS Sort number is a duplicate of an existing task. The number corrects after refreshing the page
Steps to recreate
- Log in to MUX
- Create or open a project
- Go to Tasks module
- Add three tasks
- Click the Columns flyout
- Add WBS Sort to the columns
- Right click the 2nd task and choose Insert Sibling
Expected Result - The WBS Sort number is unique
Actual Result - The WBS Sort number on the new task shows 3 which is a duplicate of one of the existing tasks
Workaround: Refresh the page
Resolution
Created DE153047 as a usability issue. This is currently targeted for 16.3