Updating task start date is not updating the successor tasks
book
Article ID: 374593
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
Updating the Start date on tentative schedule does not shift successor tasks
Steps to Reproduce:
- Log in to MUX
- Create a new project
- Add 3 tasks with Start/Finish dates
- 8/1 - 8/8
- 8/9 - 8/15
- 8/16 - 8/22
- Go To Tasks Timeline view and make task 2 successor to task 1 and task 3 successor to task 2
- Click Actions drop down>>Create tentative schedule
- Update the start date for task 1 for one day. (i.e. 8/1/24>>8/2/24)
Expected Results - The successor tasks will update their start date
Actual Results - The Finish date for task 1 is updated but the successor tasks 2 & 3 dates are not updated.
Additional Information
Workaround -
Update the task finish date and the successor tasks will update.
Feedback
thumb_up
Yes
thumb_down
No