Modern UX - 'Duration' does not roundoff correctly
book
Article ID: 373846
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
Steps to Reproduce:
- Navigate to Modern UX -> Projects Grid
- Open a Project -> Tasks tab
- Create a Task in it
- Display 'Duration' column in the Tasks Grid
- Click on 'View Options'. Change decimal precision to '0.00' against the following fields:
- 'Money Decimal Display'
- 'Number Decimal Display'
- Open 'Details' flyout. Choose the Task from step 3
- Configure the flyout. Display 'Duration' field
- Change 'Duration' to '3.8'
Expected Results: 'Duration' gets set to '4', like in PPM Gantt
Actual Results: 'Duration' gets set to '3'.
Environment
Latest version tested: 16.2.2.
Resolution
DE131212 is fixed in 16.3.0.