If a user has access to a CIT and has the Global Rights (for the CIT) Task Management - All they are not able to assign resources from the task page on the CIT. They can however assign the resources from the task details flyout / assignments.
STR:
1. As admin create a CIT and assign some resources (my example is CIT1)
2. Assign these rights to a resource - Note that CIT1 is the CIT for this example
3. Log in as that resource and navigate to the CIT.
- Make sure that the Tasks module is available on the blueprint
4. Go to the Tasks Grid
5. Add Assigned Resources as a column on the grid
6. Click on this field to choose resources
Expected Result: Resource List Shows
Actual Result: No Records are returned
Workaround: Go to the task's details flyout and assign resources there.
Reported as DE116201. Fixed in 16.3