Problem:

If you run Auto Schedule more than once it keeps changing the result in OWB. If the data is the same then ideally once Auto-schedule has been executed it should not be changing the data no matter how many times the Button is clicked. 

Steps to Reproduce: 

  1. Go into CA PPM and create one main project 
  2. Create one task for this main project 
  3. Assign a resource (example m_testuser)  to the task for this main project 
  4. Create one sub project 
  5. Create one task for this sub project and assign the same resource which is 'm_testuser' to the task 
  6. Open the main project into OWB from CA PPM 
  7. In OWB run Auto schedule and it updates the Gantt appropriately. 
  8. Run Auto Schedule again 

Expected result: After running Auto Schedule the second time nothing should change in the Gantt

Actual result: After running Auto schedule the second time the Gantt changes again

Cause:

Caused by CLRT-77927

Resolution: 

Resolved in CA PPM 14.3 

Additional Information: 

Reference the Customer Reported Defect Resolution Policy for CA PPM   

 