Cost Plan 'Could Not Load Total Row' error
search cancel

Cost Plan 'Could Not Load Total Row' error

book

Article ID: 372058

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

Steps to Reproduce:

  1. Login to New UX
  2. Navigate Projects
  3. Pick a Project -> Navigate to Financials -> Cost Plans -> Cost Plan per period metric should be populated
  4. Under Cost Plan Details, make sure that "Show Total Row" is checked
  5. Create New Cost Plan -> Open the newly created cost plan

Expected Result: Cost Plan should open properly

Actual Result: Cost Plan opens with a error “Could Not Load Total Row”

Environment

16.2.x, 16.3.x

Resolution

DE116168 is fixed in version 16.3.0