Unable to fill Timesheets by specifying a number in the 'Total' column
search cancel

Unable to fill Timesheets by specifying a number in the 'Total' column

book

Article ID: 370984

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

It has been noticed that it is not possible to fill time against a row automatically by specifying a value against the 'Total' column. For example, by specifying '5' against the 'Total' column, it is not possible to split that value into '1' against each working day in the Timesheet.

Resolution

  • There is a field called "Allow entry of line item totals" visible at Classic UI -> Administration -> Timesheet Options -> 'Modern UX Options'
  • If this field is set to True, then it will be possible to enter time against the 'Totals' column, and let the application split it evenly across the dates displayed in the Timesheet.