Unable to fill Timesheets by specifying a number in the 'Total' column
book
Article ID: 370984
calendar_today
Updated On:
Products
Clarity PPM On PremiseClarity PPM SaaS
Issue/Introduction
It has been noticed that it is not possible to fill time against a row automatically by specifying a value against the 'Total' column. For example, by specifying '5' against the 'Total' column, it is not possible to split that value into '1' against each working day in the Timesheet.
Resolution
There is a field called "Allow entry of line item totals" visible at Classic UI -> Administration -> Timesheet Options -> 'Modern UX Options'
If this field is set to True, then it will be possible to enter time against the 'Totals' column, and let the application split it evenly across the dates displayed in the Timesheet.